GENERAL CONTRACTING SCOPE OF SERVICES

Bidding Phase

  • Establish a qualified bidders list for review by the owner if required.
  • Review bids with Construct Cost budgets.
  • Receive a final notice to proceed with the work from the owner.
  • Award all contracts
  • Update the final construction schedule to reflect actual deliveries and completions along with incorporating Owner purchases of materials and equipment, if any, requiring long lead time procurement.

Construction Phase – Administration of the Construction Contract

  • Manage the ongoing construction with the continuation of the Project Manager and a full time on site Superintendent.
  • Assist the owner in selecting and retaining the professional services of surveyors, special consultants, and testing laboratories for those tests for which the Owner is responsible.
  • Establish regular on site meetings times.
  • Process timely payout requests to the owner.
  • Process Change Orders as required.
  • Work with the Owner for receiving deliveries and storage, protection and security of the Owner-purchased materials which are part of the project.

Construction Phase – Close Out

  • Conduct final inspections to determine Substantial Completions and Certificate of Occupancy from local municipalities.
  • Complete a detailed punch list.
  • Issue final Certificate for Payment
  • Collect and turn over all necessary warranty information, operation and maintenance manuals to the Owner.
  • Collect and review all as built marked up sets of drawings to be turned over to the Owner.
  • Provide all necessary training for operation and maintenance of installed equipment or systems.